• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
  • SUBSCRIBE
  • ADVERTISE
  • NEWSSTANDS
  • ABOUT
  • STAFF
  • CONTACT
  • BUSINESS DIRECTORY

Methow Valley News

Locally grown, internationally known

  • NEWS
  • ARTS
  • SPORTS
  • BUSINESS
  • OPINION
    • Letters to the Editor
    • No Bad Days
    • Editorials
    • Hello?
    • My Turn
    • Harts Pass
    • Cartoons
  • OBITUARIES
  • VALLEY LIFE
    • Mazama
    • Winthrop
    • Twisp
    • Lower Valley
    • Off the Wall
  • SENIORS
  • CALENDAR
  • LEGALS
  • CLASSIFIEDS
  • MORE…
    • Crosswords
    • Sudoku
    • Announcements
    • Photos
    • Naked Eye
    • Special Features
    • Readers Write
  • FACEBOOK

Appeals filed over Lloyd Logging gravel pit application conditions

October 15, 2026 by Marcy Stamper

County hearings examiner sets process schedule

The Okanogan County hearing examiner is considering two appeals regarding a gravel pit operated by Lloyd Logging 1 1/2 miles west of Winthrop.

One appeal is by Lloyd Logging, which is challenging some of the conditions that Okanogan County imposed in its preliminary approval of the company’s application to expand the pit from 10 to 41.84 acres and re-start excavating gravel and sand there.

The other appeal has been filed on behalf of five neighbors of the pit. The neighbors contend that a gravel pit cannot exist at that site at all because Lloyd Logging failed to renew its permit for a gravel pit and related operations after that permit expired in 1989 and zoning there has since changed.

Cascade Concrete currently uses the Lloyd Logging site to crush rock excavated from two nearby pits, one owned by the state Department of Natural Resources (DNR) and another that’s privately owned. At present, Lloyd Logging is permitted only to crush rock at the site, not to excavate there.

In its appeal, Lloyd Logging points to Cascade Concrete’s operation of the pit with “an unblemished 34-year history of operating a safe, compliant and community-minded mineral extraction and crushing facility,” attorneys with Kutak Rock LLP said on behalf of the company.

The county’s conditions restrict operations to the hours of 7 a.m. to 5 p.m., limit noise, and ban the use of jake breaks on the highway. They limit the number of round trips to and from the pit to an average of 50 per day, with a maximum of 80.

Lloyd Logging accepts some of the county’s conditions, but says others would make the operations too costly to be viable. Some conditions, including regulating traffic on a state highway, exceed the county’s authority, Kutak Rock contends. Restrictions on hours of operation are acceptable as long as there are provisions for emergency operations.

Noise restrictions on compression brakes are acceptable, although they can’t be applied to third-party equipment nor to vehicles on a state highway. Limiting the number of trips per day is unworkable because volume is based on customer need, Lloyd Logging said.

The county’s conditions limit the height of stockpiles to 20 feet, but Lloyd said the piles at the site have consistently been over 40 feet high since the start of operations. Cutting that in half would require they double the number of piles, which is not workable, Lloyd said.

In addition, restrictions on blasting and crushing during the winter, intended to protect mule deer, are unrealistic. Current staff at the pit have found that mule deer are “wholly habituated” to the pit, Kutak Rock said on behalf of Lloyd Logging.

Lloyd’s appeal includes statements from several local contractors who rely on the sand and gravel they obtain from the facility.

Neighbors: no pit allowed at all

Because county zoning for the area changed in 2000, all gravel excavation, processing and trucking are prohibited there unless an existing pit had been grandfathered in, said attorney Peter Goldman, who’s handling the appeal for the neighbors.

But after the conditional-use permit (CUP) expired in 1989, Lloyd Logging never formally sought to renew or modify the permit for the next 11 years, Goldman said. In fact, Lloyd waited more than 23 years to apply for an expansion of the pit.

In the meantime, Lloyd Logging expanded the pit from 10 to 16.2 acres without a permit, Goldman contends. Both Okanogan County and DNR issued stop-work orders when activity resumed at the pit three years ago without valid permits or a site-reclamation plan, Goldman said.

Since then, Lloyd Logging applied to Okanogan County in 2024 to restart the pit and expand it from 10 to 24.88 acres. The company subsequently modified the application to expand to 51.84 acres.

Public input

Some 150 people commented to Okanogan County on the initial environmental review of the proposed expansion. Many cited concerns about aesthetics, dust, and about whether permits were up to date, according to a spreadsheet of comments and responses prepared by the county’s Planning Department.

Some people said the pit would have a “negative impact” on quality of life and property values and want provisions that would screen the pit from the scenic Highway 20 corridor. Most commenters expressed concern about the expansion and lapses in permits.

But other commenters said the pit is essential to ensure future availability of construction in the valley and said it’s important to have a local source of gravel.

Hearing examiner schedule

Hearing Examiner Andrew Kottkamp will hear the two appeals this month. After considering the appeals, Kottkamp will consider input on the conditions for operation of the pit.

Kottkamp held a pre-hearing conference on Sept. 30 with Okanogan County’s chief civil deputy prosecutor and representatives from the county’s Planning Department; Lloyd Logging attorneys Kutak Rock LLP; and Goldman, representing the neighbors.

Kottkamp is currently reviewing all pre-hearing motions and responses from Lloyd Logging and the neighbors. He will issue a decision based on the written submissions on Oct. 21.

Kottkamp has set deadlines for witness lists, exhibits and briefings from Lloyd Logging and the neighbors in November. The county’s staff report, witness list and briefing are due at the end of November. 

Kottkamp has scheduled a three-phase hearing on Dec. 10. Phase 1 is Lloyd Logging’s appeal of the conditions Okanogan County placed on operations at the pit. Phase 2 is the neighbors’ appeal of the existence of the pit given the lapsed permits and zoning change. Phase 3 is a hearing on Lloyd Logging’s underlying application for a conditional-use permit. That phase includes the public, who are invited to provide testimony.

Kottkamp has set strict limits on the duration of testimony, the length of written documents and cross-examination. He said he may make an unannounced site visit to the gravel pit.

Final summations from all parties will be due in late December and January. Kottkamp plans to issue his decision on Feb. 10.

For more information or to comment

The deadline for public comments on the CUP is Monday, Dec. 7. The hearing is Thursday, Dec. 10, at 9 a.m. in the commissioners’ hearing room in Okanogan. People can also attend the meeting via Microsoft Teams. The link is on the hearing notice.

People can view the documents on the matter on the Planning Department website under “Projects & Plans” and then “Lloyd Logging CUP 2023-9.”

Comments and questions should be directed to Planner Pam Wyllson at (509) 422-7122 or pwyllson@okanogancounty.gov.

Filed Under: NEWS

Primary Sidebar

Today

Twisp, WA
39°
Partly Cloudy
7:05 am4:24 pm PST
Feels like: 37°F
Wind: 4mph ENE
Humidity: 90%
Pressure: 29.47"Hg
UV index: 1
SatSunMonTue
52°F / 41°F
48°F / 32°F
48°F / 27°F
45°F / 30°F
powered by Weather Atlas

Footer

© 2026 · Methow Valley News