Chewuch Canal shareholders without water on Friday

Water in the Chewuch Canal below Pearrygin Lake was shut off on Thursday evening (May 15), and expected to be flowing again by the end of the day on Friday, according to Chewuch Canal Company (CCC) President Roger Rowatt. The ditch was turned off in order to fix a faulty valve where the “old system...
Work proceeding on canal company project at Pearrygin Lake

Work proceeding on canal company project at Pearrygin Lake

By Laurelle Walsh
A temporary cofferdam is holding back Pearrygin Lake until new intake structure is built to allow the Chewuch Canal Company to fill or withdraw water from the lake.
Construction set to begin on final phase of Chewuch Canal project

Construction set to begin on final phase of Chewuch Canal project

By Laurelle Walsh
As soon as the ditch is turned off Oct. 1, work will begin on improvements to the Chewuch Canal